The Interconnection Process

Step-by-step journey from project concept to grid connection

The 6-Step Interconnection Process

The interconnection process is a structured, multi-phase journey that ensures renewable energy projects can safely and reliably connect to the electrical grid. Each step builds upon the previous one, with increasing levels of detail and complexity.

The process typically takes 1-3 years and costs $200,000 - $2 million, depending on project size and complexity. Fast-track processes exist for smaller projects with minimal grid impact, while larger projects requiring significant infrastructure upgrades follow the full study process.

Interactive Study Flow Simulator

Select Interconnection Path

Interconnection Study Flow

1
Initial Application
1-2 weeks

Submit interconnection request with basic project information

Cost: $5,000 - $15,000
Requirements: 4 items
Requirements:
  • Project location
  • Generation capacity
  • Point of interconnection
  • Basic system specs
2
Feasibility Study
4-8 weeks

Preliminary analysis of grid impact and interconnection feasibility

Cost: $25,000 - $75,000
Requirements: 3 items
3
System Impact Study
8-16 weeks

Comprehensive analysis of project impact on grid reliability and stability

Cost: $100,000 - $300,000
Requirements: 4 items
4
Facilities Study
12-24 weeks

Design of required grid upgrades and interconnection facilities

Cost: $150,000 - $500,000
Requirements: 4 items
5
Construction & Commissioning
6-18 months

Build interconnection facilities and commission the system

Cost: $500,000 - $2M+
Requirements: 4 items
6
Final Approval & Energization
4-8 weeks

Obtain final regulatory approval and energize the interconnection

Cost: $10,000 - $25,000
Requirements: 4 items

Process Optimization

Fast-track processes for smaller projects can reduce timeline by 40% and costs by 50%. Larger projects requiring significant grid upgrades follow the complex interconnection path with extended timelines.

Critical Milestones

Application Submission

Complete interconnection request with all required technical documentation and fees.

Study Phase Completion

All technical studies completed with approved interconnection facilities design.

Construction Start

Begin construction of approved interconnection facilities and grid upgrades.

Commercial Operation

Project fully operational and delivering clean energy to the grid.